|
Benefits of the Act:
-
Disputes are resolved promptly through the adjudication process and
not at the end of the job, as has been the case in the past.
-
The
Act provides for speedy out-of-Court processes for non-payment of
progress claims. If the progress claim debt is not contested within
ten days, it is deemed to be admitted. If it is disputed and notice
is given within the ten days, there is an out-of-Court adjudication
procedure.
-
It
provides a ban on "pay when paid" or "pay if paid" clauses in
contracts.
-
Contract workers can obtain a Court judgment quickly without a Court
hearing and will also be entitled to stop further work until paid.
It
is important for subbies to seek advice early in disputes about
payment, as there are strict statutory time limits that prevent late
claims being lodged. If claims are not lodged within time, subbies will
lose valuable legal rights to payment.
This
Act does not apply to contracts between a residential property owner and
a contractor in relation to work on the owner's own home.
How
it works
The process involved in getting paid is three stages and there are
strict time limits on all three stages.
| 1. |
A Payment Claim
Notice must be issued and served. The notice must: |
| |
- Identify the
construction work to which the Payment Claim relates.
- Indicate the amount of
money claimed & the payment period relating to the
invoice amount.
- State that the claim is
made under the Building and Construction Industry
Security of
Payment Act 1999 (CFMEU can provide labels available
to help with this).
|
| 2. |
It is also very
important to serve the claim properly. It should be
delivered by hand to the principal place of business of
the Debtor (principal contractor).
|
| 3. |
The Debtor then
has 10 business days to either pay the claim or serve the
contract worker with a Payment Schedule. If they do not
respond within the time period, they are assumed to have
admitted the amount claimed. There can be no extension of
this time. In that case the Claimant can go straight to the
Court to obtain a judgment without having to argue a case.
|
| 4. |
If the Debtor
disputes the amount claimed, they must respond by serving
the contract worker (the Claimant) with a Payment Schedule
within 10 working days. The Claimant then has five business
days to apply for adjudication. If the Claimant does not do
this within the five days they lose the right to
adjudication under the Act, and the right to suspend work.
There is nothing in the Act however, to stop a Claimant
lodging a fresh payment claim and starting again. |
The
adjudication process can be done by an adjudicator agreed between the
parties or an Authorised Nominating Authority (ANA) can appoint the
adjudicator. A list of ANA's is available from the Union Office.
The
adjudicator must determine the application as quickly as possible. The
adjudicator’s decision is final and, if in favour of the applicant, the
Order can then be legally enforced. |